Title: Resurfacing Kirtland Road (CH-17), in Chardon Township Sponsor: Geauga County Engineer Name: GEA Kirtland Road (Sections A-G) Estimated Total Cost: $350,000 Proposed Source of Federal Funds: NOACA
History/Background: Kirtland Road was last improved in 1995. The proposed project has been reviewed by the Geauga County Board of Commissioners in open session
Current Conditions: Kirtland Road is functionally classified as a urban collector. It is a two-lane facility with 11-foot wide lanes and 3 feet wide stabilized shoulders. The legal speed limit is 40 miles per hour (mph). The average daily traffic (ADT) is 2,820 vehicles per day. The accident rate is 0.20 accidents per million vehicle miles (1997 –1999).
Proposed Project: This project involves resurfacing the existing asphalt pavement on 1.62 miles of Kirtland Road, from the Geauga County line to US-6 (G.A.R. Highway) in Chardon Township. The pavement width will remain twenty-two (22) feet with three (3) feet wide stabilized shoulders.
Eighty percent ($280,000) of the construction (C) cost will be funded with Surface Transportation Program (STP) funds administered by NOACA. The non-federal share of construction ($70,000) will be provided by the Geauga County Engineer. Preliminary engineering (PE) and right-of-way (RW) costs will be borne by the sponsor. The project will be designed by county engineer staff and ready to construct for SFY 2005. The county engineer will request to administer the project following agreement with ODOT.
Your comments are welcome on the above proposed transportation improvement projects. Please notify us if you would like to be added to our email notification list for future updates.
If you are a governmental entity and would like to comment on a project, please email us.
Staff Comment (Summary):
Intergovernmental Review (IGR):
Public Involvement:
Committee Review:
Bicycle Advisory Subcommittee: No additional bike accommodation requested at this time. In the future, when major work is done on this road, BASC recommends a 4' paved shoulder. |