Governing Board approved on 6/15/01 with Resolution 2001-040
Title: Painting Various Bridges in Cuyahoga and Lake County Sponsor: Ohio Department of Transportation (ODOT) District 12 Name: CUY IR 77-7.56/VARIOUS: PID No. 21787 Estimated Total Cost: $670,000 Proposed Source of Federal Funds: ODOT
History/Background: This project is included in ODOT District 12's SFY 2003 Bridge Program.
Current Conditions: IR-77, IR-90, IR-480 and IR-490 are functionally classified as interstates. The speed limits are 55 miles per hour (mph). The average daily traffic (ADT) varies. US-6 and US-422 are functionally classified as minor and principal arterials respectively.
Proposed Project: This project involves painting ten (10) bridges at various locations along IR-77, IR-90,US-422 and IR-480, in Cuyahoga County and IR-90 and US-6, in Lake County. Traffic will be maintained.
Ninety percent ($603,000) of the construction (C) cost will be funded from ODOT's District pavement allocation of Interstate Maintenance (IM) funds. ODOT will fund the ten percent ($67,000) non-federal share.
Your comments are welcome on the above proposed transportation improvement projects. Please notify us if you would like to be added to our email notification list for future updates.
If you are a governmental entity and would like to comment on a project, please email us.
Staff Comment (Summary): Staff recommends approval of this preservation treatment understanding that traffic will be maintained during work phases.