On March 12, 2010 the NOACA Governing Board approved the following regarding this project:
Resolution No. 2010-008 Project Planning Review
Resolution No. 2010-009 Plan and TIP Amendment.
Title: Resurface Auburn Road in Newbury and Munson Townships
Sponsor: Geauga County Engineer
Estimated Total Cost: $500,000
Proposed Source of Federal Funds: NOACA
History/Background: On December 15, 2009, the Board of County Commissioners, Geauga County, Ohio approved Resolution No. 09-222, to improve sections K - M of Auburn Road (CH 4) in Newbury and Munson Townships.
Current Conditions: Auburn Road is a two-lane facility. The pavement width is 26 feet, with lanes 11 feet wide and paved shoulders, two feet wide. Auburn Road is functionally classified as a rural major collector. The speed limit is 45 miles per hour. The average daily traffic is 7,200 vehicles per day with 3.2% percent trucks (2009).
Proposed Project: This project involves resurfacing the lanes and shoulders along 2.67 miles of Auburn Road (sections K-M), from Fairmount Rd to Mayfield Road in Newbury Township and Munson Township (location map). The estimated construction cost is $500,000. The sponsor requests eighty percent ($400,000) of the construction cost be funded with NOACA-administered Surface Transportation Program funds. The Geauga County Engineer will provide the non-federal share of construction ($100,000). The county engineer will request to administer the project following local standards. The project is designed and can be ready to construct by July 2012.
Staff Comment (Summary):
Plan and Transportation Improvement Program (TIP) Team:
- This project is consistent with NOACA’s Connections 2030 Goal #3 (Preserve and Improve the Efficiency of the Transportation System) and ODOT’s Access Ohio 2004 - 2030 Goal #4 (System Preservation).
- Recommend committee and public review in order to obtain comments.
Regional Transportation System (RTS) Team:
- In 2008 pavement condition rating (PCR) on this section of Auburn Road ranged between 71 - 78 (fair to good condition). In construction year 2012 the RPMS (Regional Pavement Management System) predicts the PCR will range between 58 - 64 (fair to poor condition). The RPMS also recommends major rehabilitation on this section of Auburn Road in 2012.
- This project as proposed does not meet federal guidelines for adequate bicycle accommodation. However, it’s a resurfacing only project.
Intergovernmental Review and Consultation (IGRC):
If you are a representative of a governmental entity and would like to comment on this project, please email us.
"I am in favor of this needed resurfacing project." - Munson Township Trustee
"Certainly a worthy project in Munson township." -
Munson township trustee
Public Involvement:
NOACA encourages comments from the public on this proposed transportation improvement project. Please notify us if you would like to be added to our e-mail notification list for future updates.
Committee Review:
Regional Transportation Investment Subcommittee (RTIS)/Transportation Advisory Committee (TAC):
-
No comments; recommended for amendment to NOACA's Transportation Plan .
Bicycle Advisory Council (BAC):
- This project as proposed does not meet federal guidelines for safe bike accommodation, but it’s a resurfacing-only project. If possible, pave wider shoulders. Post “Share the Road” signs.
|
|
|